Assemblies

Making one item pull others along with it, so measuring the parent measures the build-up.

An item can include others. Measure the parent and the children come with it: draw 100 SF of a paving assembly and the stone, the binder and the tack coat under it are all measured at once.

Attaching a child

Attach the child to the parent from the item list, then set the rate: how much of the child there is per unit of the parent, plus an adjust multiplier for waste on that relationship alone.

Two rules decide whether the attach is allowed:

The rate belongs to the relationship

This is the part worth understanding, because it is what makes assemblies usable on a real job.

The rate is stored on the relationship, not on the child. The same aggregate can therefore ride one rate under a road section and a different one under a pad - one item in the list, included twice, at two rates. Editing one does not touch the other.

Pinning a unit

By default the relationship reports in the child's own unit and follows it: change the child's unit and the inclusion changes too. Pin a unit on the relationship to stop that, so a change to the child no longer ripples into this one parent.

Notes